Lesson 5.3

Snagging

ch05-l03-img02 course image doors and windows must be opened, closed, locked and checked for alignment rather than judged only by appearance.

Handover is an operating test, not a photoshoot.

Educational architectural illustration showing doors and windows must be opened, closed, locked and checked for alignment rather than judged only by appearance
Doors and windows must be opened, closed, locked and checked for alignment rather than judged only by appearance.

Know what was built. Know that it works. Keep the information needed to look after it.

01 What Is A Snag?

What Is A Snag?

A snag is something that still needs:

Educational architectural illustration showing snagging checks physical performance across floors, walls, ceilings, bathrooms, electrical points and joinery
Snagging checks physical performance across floors, walls, ceilings, bathrooms, electrical points and joinery.

correction

completion

adjustment

or

repair

before final acceptance.

Examples:

Door rubs against floor.

Socket does not work.

Paint patch is unfinished.

Drawer hits another shutter.

Shower water flows toward the door.

Window does not lock properly.

Each becomes a snag.

02 Go Room By Room

Go Room By Room

Do not try to remember everything.

Educational architectural illustration showing snagging should proceed room by room using a repeatable checklist rather than memory
Snagging should proceed room by room using a repeatable checklist rather than memory.

Use a systematic route.

For example:

GROUND FLOOR

Living.

Dining.

Kitchen.

Bedroom.

Bathroom.

Utility.

Then:

FIRST FLOOR

Bedroom 1.

Bedroom 2.

Bathrooms.

Balcony.

Terrace.

This prevents random inspection.

03 Doors

Doors

Operate every one.

Check:

  • smooth opening
  • smooth closing
  • latch
  • lock
  • stopper
  • hinge
  • floor clearance
  • alignment.

A door that only closes when slammed is not complete because it has beautiful veneer.

04 Windows

Windows

Open.

Close.

Lock.

Inspect:

  • movement
  • handles
  • seals
  • glass
  • scratches
  • frame damage
  • drainage paths where relevant.

If possible, check water-sensitive windows during or after rain rather than relying only on appearance.

05 Flooring

Flooring

Look for:

  • cracks
  • chips
  • stains
  • uneven joints
  • damaged skirting
  • awkward cuts
  • transitions
  • loose or hollow-sounding areas where relevant to the installed system.

Wet areas deserve extra attention.

06 Walls & Ceilings

Walls & Ceilings

Look in normal light.

Then look with light falling across the wall where useful.

Check:

  • paint consistency
  • cracks
  • unfinished patches
  • damp marks
  • poor edge work
  • ceiling joints
  • access panels.

Do not obsess over microscopic imperfections.

Look for things that affect the actual finished quality.

07 Bathrooms

Bathrooms

Use them.

Run:

  • basin
  • shower
  • health faucet
  • WC
  • hot water.

Check:

  • drainage
  • leaks
  • flow
  • shower partition
  • vanity drawers
  • mirror
  • exhaust
  • accessories.

Pour or run enough water to see where the floor actually sends it.

08 Electrical

Electrical

Operate:

EVERY SWITCH

Test:

EVERY SOCKET

Check:

  • lights
  • fans
  • regulators
  • dimmers
  • USB points
  • automation
  • major appliance points where installed.

Also check whether the distribution board is clearly identified.

You should not have ten anonymous breakers and no idea what they control.

09 Joinery

Joinery

Open every:

drawer

wardrobe

cabinet

kitchen shutter

Look for:

  • rubbing
  • loose hinges
  • alignment
  • damaged laminate/finish
  • hardware operation
  • soft-close function where included
  • unfinished edges.

If it moves, move it.

10 The Snag List

The Snag List

Do not writeBathroom issue.
WriteMaster Bathroom – Shower Area – water remains beside door after shower test.

Or:

Bedroom 2 – wardrobe left shutter – rubbing against lower drawer.

Include:

  • room
  • exact location
  • problem
  • photo
  • date.

That gives the contractor something precise to close.

11 Open Vs Closed

Educational architectural illustration showing every snag should have a precise location, evidence, responsible party, status and verification before closure
Every snag should have a precise location, evidence, responsible party, status and verification before closure.

Open Vs Closed

Every snag should eventually become:

OPEN

or

CLOSED

Do not delete completed items.

Mark them closed.

That leaves a record.

12 Check Your Understanding

Snagging is an operating test.

A drawer looks perfectly aligned. What should you do?

Assume it works

Open and close it

Handover is an operating test, not a photoshoot.

Ownership begins when the project information, controls and maintenance knowledge become yours.

Apply the idea

Close a snag properly.

Complete the decision to finish this scene.

  1. Assign and correct it
  2. Record room and exact location
  3. Retest, verify and mark closed
  4. Describe and photograph the fault