Lesson 5.2
Document What Gets Hidden
ch05-l02-img02 course image concealed floor, wall and ceiling systems should be photographed before each covering layer hides them.
Record what you will eventually stop being able to see.

Know what was built. Know that it works. Keep the information needed to look after it.
01 Before Plaster
Before Plaster
Photograph walls while electrical and plumbing routes are visible.
Useful photographs may show:
- conduit routes
- electrical boxes
- water lines
- drainage
- AC pipes
- data cables.
Try to capture enough of the room that you can understand where the route is later.
A photograph showing only a pipe with no context is less useful.

02 Before Flooring
Before Flooring
Where relevant, record:
- plumbing routes
- floor services
- waterproofing
- drain positions
- underground lines
- tank work.
Once screed and flooring cover them, exact positions become harder to identify.
03 Before False Ceiling
Before False Ceiling
Photograph:
- electrical routes
- AC ducts
- drain lines
- automation modules
- speakers
- access zones
- junction locations.
Photograph the ceiling before the ceiling disappears.
04 Waterproofing
Waterproofing
This deserves its own record.
Take photographs of important areas before tiling or backfilling:
- bathrooms
- balconies
- terraces
- tanks
- below-ground work.
Where available, also retain:
- product details
- contractor information
- warranty
- testing records.
Years later, this can help identify what system exists under the finish.
05 Record Changes
Record Changes
The drawing is only useful if it still matches reality.
Imagine a plumbing line was shifted on site.
The original drawing still shows the old route.
If nobody records the change, the drawing becomes misleading.
So important changes should be reflected in:
- marked-up drawings
- revised drawings
- written records
- photographs.
06 Keep Approvals For Changes
Keep Approvals For Changes
Some changes affect:
price
design
performance
Before proceeding, record:
- what changed
- why
- additional or reduced cost
- who approved it.
This prevents:
“I thought that was included.”
and:
“Nobody told me it was changing.”
07 Product Information
Product Information
Save labels or photographs of major products where useful.
For example:
paint shade
tile code
laminate code
sanitaryware model
tap range
switch range
window system
hardware
You do not need a museum of packaging.
Just enough information to identify replacements later.
08 Name Your Files Properly
Name Your Files Properly
Instead of:
IMG_4837.jpg
use something like:
Master Bathroom - Plumbing Before Tiling - Aug 2026
Instead of:
drawing-final-final2.pdf
use:
First Floor Electrical - Rev 04 - Issued for Construction
Simple naming makes the archive far more useful.
09 The Concealed-Work Map
The Concealed-Work Map
A particularly useful end-of-project record can combine:

final drawing
-
photographs
-
notes
For example:
MASTER BEDROOM TV WALL
- socket location
- conduit route
- data point
- AC drain route
- photograph before plaster.
You are effectively creating an X-ray of the house.
10 Check Your Understanding
What should be recorded before it disappears?
Five years later you want to drill for a cabinet. Which record is more useful?
Context photo of concealed routes
Finished-room photograph
Record what you will eventually stop being able to see.
Ownership begins when the project information, controls and maintenance knowledge become yours.
Apply the idea
Create a useful hidden-services record.
Complete the decision to finish this scene.
- Label the route and date
- Photograph before plaster or closure
- Store it with the final project file
- Include a fixed room reference